Steam was required for the mine mill after smelting operations were discontinued. As a solution, a new 30 MW Cleaver-Brooks boiler was installed, including a new substation transformer, high voltage apparatus, switchgear, and DCS integration. Responsible for leading the commissioning of all DCS controls, 110 kV apparatus, and 13.8 kV switchgear.