Business Case & Scope Definition for 113km of Line
•
Distribution Planning has a capital budget for system improvements, aimed at ensuring SaskPower’s capacity to provide reliable power. I analyzed data and defined the scope for 113 km of line rebuilds, valued at approximately $10M.
-
Strategic improvement of highway powerline crossings results in safety & efficiency
•
“What should we do with all the power lines that cross highways and interfere with oversized tall loads?” At first, this seems like a straightforward problem with a simple solution: “Bury everything underneath the highway!” However, a more strategic examination…
-
Change Management Prevents $3.8M Sunk Costs
•
In September 2022, when I assumed the role of Acting Program Manager, $6.6 million worth of cross-arm replacement projects had been designed, tendered, and were awaiting increased spending approval. Actual costs exceeding estimates prompted an investigation into the business case…
-
118km of URD Replacement in 46 Areas
•
Urban Residential Distribution in collaboration with the construction of SaskTel’s Infinet fiber network was at the program peak in 2020-21. It was the second largest Distribution Asset Management & Planning program at $18.3M. The scope was to design and install…
-
Replacement of Obsolete M-series RTU and failed SER with Next Gen SCADA
•
The project scope included installing the entire fiber optic network, IRIG-B timing, and replacing the GE M-Series RTU, which had approximately 150 controls, indications, alarms, SERs, and 18 analog measurements. This was replaced with a GE D400 HMI equipped with…