Business Case Cellular Change Management Chemical Commissioning Construction CP&C DCS Design Emergency Repair Environment Fiber Optics Grounding and Bonding IR Imaging Load Flow Logistics Maintenance Testing Microwave Mining Oil & Gas Overhead Power Generation Power Line Carrier Power Quality Protection Coordination Prototype QAQC Right of Way Safety SCADA Scalability Scope Definition SubStation Training Transmission Troubleshooting Underground VFD Wind Energy

  • 25kV service: critical path for Aspen Power Plant construction

    25kV service: critical path for Aspen Power Plant construction

    SaskPower

    2023

    Build ~25 km of three-phase line and install a transformer to service the construction site of SaskPower’s new 370 MW natural gas power plant.

  • Change Management Prevents $3.8M Sunk Costs

    Change Management Prevents $3.8M Sunk Costs

    SaskPower

    2022

    In September 2022, when I assumed the role of Acting Program Manager, $6.6 million worth of cross-arm replacement projects had been designed, tendered, and were awaiting increased spending approval. Actual costs exceeding estimates prompted an investigation into the business case…

  • Richard Road Rebuild – Multiphase 33km Pelican 3phase Backbone

    Richard Road Rebuild – Multiphase 33km Pelican 3phase Backbone

    SaskPower

    2020

    Approximately 1 km of the line was submerged in a slough, and with spring ice breakup expected in six months, the reliability risks were increasing. The project scope was divided into three phases, prioritizing risk mitigation, as completing the entire…

  • 118km of URD Replacement in 46 Areas

    118km of URD Replacement in 46 Areas

    SaskPower / SaskTel

    2021

    Urban Residential Distribution in collaboration with the construction of SaskTel’s Infinet fiber network was at the program peak in 2020-21. It was the second largest Distribution Asset Management & Planning program at $18.3M. The scope was to design and install…

  • N. Battleford 20km of URD Replacement

    N. Battleford 20km of URD Replacement

    SaskPower / SaskTel

    2018

    Lead the design for the replacement of 20 km of Urban Residential Distribution (URD) at a cost of $2.97 million. Drilling (boring) once, under one contract to install SaskTel’s fiber network and replace SaskPower’s URD was the flagship Crown collaboration.…

  • N. Battleford to Battleford 25kV Tie Line

    N. Battleford to Battleford 25kV Tie Line

    SaskPower

    2020

    This project was initiated due to load growth in the town of Battleford. If operations required the entire town’s power generation to be supplied from North Battleford across the river, the capacity of the existing line was insufficient. The project…

  • Root Cause Fix for Beckwith AVR Failures Caused by GPR

    Root Cause Fix for Beckwith AVR Failures Caused by GPR

    SaskPower

    2012

    Approximately once a year, four regulators north of Meadow Lake experienced failures in the Beckwith automatic voltage regulator (AVR). Due to the extremely sandy soil, O&M staff suspected that these failures were caused by Ground Potential Rise (GPR) affecting the…

  • 100km Fiber Optic Preventative Maintenance – Pilot Project

    100km Fiber Optic Preventative Maintenance – Pilot Project

    SaskPower

    2017

    For the first time since the TeleControl team at SaskPower began installing fiber optics, I initiated a preventative maintenance project to inspect and repair one of our fiber lines, which was approximately 20 years old.

  • Queen Elizabeth D-Plant Expansion

    Queen Elizabeth D-Plant Expansion

    SaskPower

    2015

    The Queen Elizabeth (QE) “D-Plant” project was an expansion of Saskatoon’s largest power plant. In terms of Communication Protection & Control (CP&C), it involved integrating a fourth location with the three existing critical locations within QE.

  • FERTILIZER SUBSTATION AND PLANT EXPANSION

    FERTILIZER SUBSTATION AND PLANT EXPANSION

    Yara International

    2009

    Increasing the electrical system by 10 MVA was required to support the demand for the planned plant expansion. The electrical scope included adding one 138 kV transformer to the customer-owned substation, four 5 kV motors, and approximately twenty 600 V…