25kV service: critical path for Aspen Power Plant construction
•
Build ~25 km of three-phase line and install a transformer to service the construction site of SaskPower’s new 370 MW natural gas power plant.
-
Richard Road Rebuild – Multiphase 33km Pelican 3phase Backbone
•
Approximately 1 km of the line was submerged in a slough, and with spring ice breakup expected in six months, the reliability risks were increasing. The project scope was divided into three phases, prioritizing risk mitigation, as completing the entire…
-
N. Battleford to Battleford 25kV Tie Line
•
This project was initiated due to load growth in the town of Battleford. If operations required the entire town’s power generation to be supplied from North Battleford across the river, the capacity of the existing line was insufficient. The project…