Business Case Cellular Change Management Chemical Commissioning Construction CP&C DCS Design Emergency Repair Environment Fiber Optics Grounding and Bonding IR Imaging Load Flow Logistics Maintenance Testing Microwave Mining Oil & Gas Overhead Power Generation Power Line Carrier Power Quality Protection Coordination Prototype QAQC Right of Way Safety SCADA Scalability Scope Definition SubStation Training Transmission Troubleshooting Underground VFD Wind Energy

  • LEDR Microwave Radio Replacement for Customer Co-Gen

    LEDR Microwave Radio Replacement for Customer Co-Gen

    SaskPower / NRgreen

    2016

    4RF Aprisa XE radios were purchased to replace two obsolete LEDR radio links used to protect Independent Power Producer (IPP) sites at Kerrobert and Loreburn. The protection scheme involved both direct tripping and comm-loss tripping functions.

  • 130km Fiber Optic Install – Critical Path to Golden Lake Success

    130km Fiber Optic Install – Critical Path to Golden Lake Success

    SaskPower

    2014

    Phase 1 of Golden Lake Substation was being constructed on an aggressive schedule, and TeleControl was positioned to materialize a massive opportunity to put the project ahead of schedule! If we could plough 130km of fiber optics, and make changes…

  • Special Protection Scheme for Customer Backup Generators

    Special Protection Scheme for Customer Backup Generators

    SaskPower / Husky

    2012

    The Lloydminster Husky Upgrader has backup generators that require periodic testing as part of a preventative maintenance plan. Backup generator operation can potentially backfeed the grid, so a special protection scheme is needed. Our five-person TeleControl team worked at both…

  • SAGD Oil Plant Bi-Annual Maintenance and Troubleshooting

    SAGD Oil Plant Bi-Annual Maintenance and Troubleshooting

    Husky Energy

    2007-2010

    As part of a contract crew, performed bi-annual electrical maintenance testing on two 25 kV oil-filled transformers, as well as 5 kV and 600 V switchgear. Additionally, in partnership with Schneider Electric, led the troubleshooting of a 5 kV reduced…

  • Electrical Maintenance Testing and Support

    Electrical Maintenance Testing and Support

    BP Canada

    2007-2010

    The gas cavern storage facility, which serves National Energy Board (NEB) regulated pipelines, maintains its operations with a tri-annual shutdown schedule. As part of a contract crew, we were responsible for the electrical maintenance and testing of the 138kV substation…