Tag: SubStation

VIEW PROJECT EXPERIENCE BY “SERVICE” TYPE

VIEW PROJECT EXPERIENCE BY TAG

Business Case Cellular Change Management Chemical Commissioning Construction CP&C DCS Design Emergency Repair Environment Fiber Optics Grounding and Bonding IR Imaging Load Flow Logistics Maintenance Testing Microwave Mining Oil & Gas Overhead Power Generation Power Line Carrier Power Quality Protection Coordination Prototype QAQC Right of Way Safety SCADA Scalability Scope Definition SubStation Training Transmission Troubleshooting Underground VFD Wind Energy

  • 25kV service: critical path for Aspen Power Plant construction

    25kV service: critical path for Aspen Power Plant construction

    SaskPower

    2023

    Build ~25 km of three-phase line and install a transformer to service the construction site of SaskPower’s new 370 MW natural gas power plant.

  • Transformer Top Rescue SOP Development

    Transformer Top Rescue SOP Development

    SaskPower

    2016

    Could we rescue a person injured while working on top of a transformer? As members of the OH&S committee we were tasked with 1) Identifying viable rescue solutions 2) Proving their effectiveness for SaskPower 3) Presenting our findings at Safety…

  • Golden Lake Substation – Phase 1 & 2

    Golden Lake Substation – Phase 1 & 2

    SaskPower

    2014-15

    To meet an aggressive schedule, Phase 1 of the Golden Lake switching station involved building a greenfield substation with a single 230kV-25kV transformer and three secondary feeders. TeleControl was the only SaskPower group involved during the construction phase, our scope…

  • Power Line Carrier Replacement at 3 Remote Northern Sites

    Power Line Carrier Replacement at 3 Remote Northern Sites

    SaskPower / Cameco

    2015

    This project exemplified how an engaged field team can drive a major project from the ground up, rather than waiting for top-down planning. After ploughing fiber from North Battleford to Meadow Lake, the TeleControl team salvaged two sets of new…

  • 230kV Customer Interconnection at Potash Mine

    230kV Customer Interconnection at Potash Mine

    SaskPower / PCS

    2016

    Utility/customer projects are always unique due to the teamwork and communication required between two organizations. This project demanded even more coordination, as it involved leading the commissioning at the mine site while simultaneously orchestrating the commissioning at three other SaskPower…

  • 138kV Customer Interconnection at Potash Mine

    138kV Customer Interconnection at Potash Mine

    SaskPower / Mosaic

    2012

    Like all large industrial customers with a transmission connection to their customer-owned substation, utility protection, metering, and control are located onsite, interfacing with their equipment at a demarcation point. The project scope included installing a fiber optic connection to the…

  • FERTILIZER SUBSTATION AND PLANT EXPANSION

    FERTILIZER SUBSTATION AND PLANT EXPANSION

    Yara International

    2009

    Increasing the electrical system by 10 MVA was required to support the demand for the planned plant expansion. The electrical scope included adding one 138 kV transformer to the customer-owned substation, four 5 kV motors, and approximately twenty 600 V…

  • 230kV Customer Owned Substation Maintenance and Support

    230kV Customer Owned Substation Maintenance and Support

    Meadow Lake OSB

    2010

    As part of a 6 person crew contracted to assemble a 75MVA, 34.5kV/138kV we assembled, vacuum filled, and commissioned under an aggressive 24 hour/day schedule.

  • Wind Farm 75MVA Collector Transformer Assembly

    Wind Farm 75MVA Collector Transformer Assembly

    Ghost Pine Wind Farm

    2010

    As part of a 6 person crew contracted to assemble a 75MVA, 34.5kV/138kV we assembled, vacuum filled, and commissioned under an aggressive 24 hour/day schedule.

  • 30MW Boiler required substation expansion

    30MW Boiler required substation expansion

    HBM&S

    2010

    Steam was required for the mine mill after smelting operations were discontinued. As a solution, a new 30 MW Cleaver-Brooks boiler was installed, including a new substation transformer, high voltage apparatus, switchgear, and DCS integration. Responsible for leading the commissioning…